Job costing for tradies: knowing whether a job made money
How NZ trade businesses can tell if a job made money: quoted vs committed vs actual vs invoiced, real labour cost, work in progress, and markup versus margin.
By Tavo teamPublished 5 min read
- Job costing
- Profit
- Quoting
Plenty of trade businesses are busy all year and still not sure which jobs made money. The bank balance goes up and down, the accountant sends a profit figure months later, and by then the jobs that lost money are long finished. Job costing is how you find out while it still matters. This guide covers what to track, how to read it, and the habits that make it work on a small crew.
What job costing actually means
Job costing is comparing what a job was meant to cost and earn with what it really did, line by line. Not just "did we make money overall this year", but "did the deck at 14 Rata Street make money, and if not, where did it go wrong".
To do that you need four numbers for every job, and it helps to keep them separate in your head.
Quoted
What you priced: the hours, materials, subcontractors and other costs you allowed for, and what you're charging the customer. This is your budget. If you quoted it carefully (our guide to writing a job quote covers that), you already have most of the numbers you need.
Committed
Costs you've agreed to but haven't been billed for yet. The timber on order, the crane booked for Thursday, the subbie's accepted quote. Committed costs are easy to forget because no invoice has arrived, but they're real, and they're often what tips a job over budget.
Actual
What has really been spent: hours worked at their real cost, materials received or billed, subcontractor and hire invoices. This is the number most people mean by "cost", but on its own it's always behind, because bills arrive late.
Invoiced
What you've billed the customer so far, through deposits, progress claims and the final invoice. Comparing invoiced against the work done tells you whether you're ahead or behind on billing.
Work in progress: the number most people miss
On any job that runs more than a week or two, there's a gap between the work you've done and the work you've invoiced. That gap is work in progress (WIP). If you've done 60% of a job but only billed a 30% progress claim, you're funding the other 30% yourself.
WIP matters for two reasons. It shows money you're owed but haven't asked for yet, which affects cash flow. And it stops you misreading a job: a job can look like it's losing money simply because the costs have landed and the invoice hasn't gone out. Our post on getting paid faster covers keeping WIP under control with progress claims.
Labour at its real cost
Labour is usually the biggest cost on a trade job, and the easiest to understate. The real cost of an hour is more than the hourly wage. It includes holiday pay and public holidays, sick leave, employer KiwiSaver contributions, ACC levies, and the hours you pay for that aren't spent on any job.
If you cost labour at the bare wage, every job looks more profitable than it is. Work out a realistic cost per hour for each person (see pricing your labour rate) and use that in your job costing.
You also need to know which job the hours went to. That comes from timesheets that record time against jobs as it happens, not a weekly total split up by guesswork on Friday.
Materials, subbies and hire
Materials are the second big cost and the one most likely to drift. Common leaks:
- Materials ordered for one job and used on another.
- Extra trips to the supplier that never get charged to a job.
- Supplier invoices that arrive weeks later and get paid without anyone checking them against the job.
- Prices that went up between quoting and ordering.
Raising a purchase order against the job when you order, and matching the supplier's bill to that order when it arrives, closes most of these gaps. Purchase orders and supplier bills has more on that.
Subcontractors, plant hire, skips and similar costs should be charged to the job they belong to, with their own line in your budget so you can see if they're running over.
Variations change the budget
When the customer asks for something extra, the job changes, and so should the numbers. An agreed variation adds to the contract value and usually to the expected cost. If you don't record it, the job will look like it ran over budget when it actually grew. See managing variations and extra work.
Markup versus margin
These two get mixed up constantly, and the difference costs real money.
- Markup is profit as a percentage of cost.
- Margin is profit as a percentage of the selling price.
For example, say a job costs you $10,000 and you add a 25% markup. You charge $12,500, and your profit is $2,500. That $2,500 is 25% of the cost, but only 20% of the price. So a 25% markup gives a 20% margin.
If you set a target margin of 25% and then apply a 25% markup to hit it, you'll fall short on every job. Decide which one you're talking about and stick with it.
Check costs during the job, not after
The biggest change you can make is timing. Looking at job costs after the final invoice is a post-mortem. Looking at them during the job gives you options:
- Labour at 80% of the quoted hours with a third of the work left? Time to talk to the crew, or to the customer about scope.
- Materials already over? Check whether something was ordered twice or used elsewhere.
- Lots of work done but not invoiced? Send a progress claim.
A useful habit is a short weekly look at every open job: hours used against quoted, costs against budget, and what's been invoiced. Ten minutes on a Monday morning catches most problems early.
Review finished jobs
When a job's done, spend a few minutes on what happened. Which lines ran over? Was the quote wrong, or did something change on site? Feed what you learn back into your next quote and your price book. Over time, your quotes get closer to reality, which is the whole point.
How Tavo shows job costing
In Tavo, the budget comes from the accepted quote. Time comes in from your crew's phones against the job (see timesheets), materials come from purchase orders and supplier bills, and other costs can be added directly to the job.
Each job's Money tab shows the contract with variations, what's been earned so far, what's been invoiced, what's not invoiced yet, cost to date, and gross profit with the margin. Bars for labour, materials (including what's on order) and subcontractors, plant and other costs show each one against the quote, with a warning when a cost reaches a level you set (90% of the quote by default). The job costing page explains it in more detail, and reports show job profit by job, customer and job type, with CSV export.
If you'd like to know which jobs make money before the accountant tells you, you can try Tavo free for 14 days.
This post is general information, not legal, tax or employment advice. Rules and rates change, so check the official source linked above or talk to an adviser, such as your accountant or a lawyer, before relying on it. Spotted something out of date? Let us know.