Purchase orders and supplier bills for trade businesses

Why purchase orders matter for NZ trade businesses, how to check orders against deliveries and bills, and how to put every supplier cost on the right job.

By Tavo teamPublished 6 min read

  • Purchasing
  • Job costing
  • Suppliers

Materials are often the biggest cost on a job after labour, and they're the cost most likely to slip through the cracks. Orders get phoned through, deliveries turn up short, prices creep up between the quote and the bill, and by the end of the month there's a pile of supplier invoices that nobody is quite sure which job they belong to. A simple purchasing routine fixes most of this. This guide covers why purchase orders are worth the effort, how to check what you're billed, and how to get every supplier cost onto the right job.

Why raise purchase orders at all?

Plenty of small trade businesses run without purchase orders for years. They ring the merchant, give the account number, and sort it out when the statement arrives. That works until the business grows, or until you want to know what a job really cost. A purchase order (PO) gives you three things that a phone call doesn't.

An agreed price

When you send a PO, you're writing down what you expect to pay. If the supplier quoted you a price, put it on the PO along with their quote reference. When the bill arrives and the price is different, you have something to point to. Without a PO, you're relying on memory, and it's hard to argue about a price nobody wrote down.

A reference on the bill

Most suppliers will put your PO number on their invoice if you give them one. That single reference makes matching bills to jobs dramatically easier. Instead of guessing which of three similar orders a bill relates to, you look up the PO number and you know the job straight away.

A committed cost on the job

The moment you place an order, that money is spent, even though the bill hasn't arrived yet. If you only count costs once bills are entered, a job can look healthy for weeks while thousands of dollars of materials are on their way. Tracking ordered but not yet billed amounts (often called committed costs) gives you an earlier, more honest view. Our guide to job costing for tradies explains why that early view matters.

The three way check: order, delivery, bill

The core of good purchasing is checking three documents against each other:

  1. The order. What you asked for, how many, and at what price.
  2. The delivery. What actually turned up on site or at the yard.
  3. The bill. What the supplier is charging you for.

When all three agree, you pay the bill with confidence. When they don't, you've caught a problem before paying for it. The most common mismatches are a short delivery that's billed in full, a price that's higher than quoted, or a bill for something you never ordered.

The check only works if somebody records what arrived. That doesn't need to be complicated: a quick note against the order when the truck leaves, or a photo of the delivery docket, is enough. The key is doing it at the time, because a week later nobody remembers whether there were 40 lengths or 36.

Part deliveries, substitutions and price changes

Real deliveries are messy. Here's how to handle the usual complications.

  • Part deliveries. Record what came and leave the rest open on the order. When the balance arrives, record that too. This stops you paying for the full order on the first bill, and it tells you what's still outstanding.
  • Substitutions. If the supplier sends a different product because the one you ordered was out of stock, check whether it's actually suitable and whether the price changed. Note the substitution on the order so the bill makes sense later.
  • Price changes. If the bill is higher than the PO, raise it with the supplier before you pay. Sometimes it's an error. Sometimes prices genuinely went up, and you'll want to know so you can update your price list and future quotes.
  • Late deliveries. Put a "needed by" date on every order. A late delivery can hold up a crew, and knowing early lets you chase the supplier or reshuffle the work.

Allocating bills to jobs

Every supplier bill should end up charged to a job, or deliberately marked as an overhead. The ones that fall in between are where job costing goes wrong.

Splitting one bill across jobs

Trade account bills often cover several jobs. A single invoice from the merchant might include timber for one job, fixings for another and some general consumables for the van. Split the bill so each job carries its share. If the bill has PO numbers on its lines, this is quick. If it doesn't, the delivery dockets usually tell you where things went.

Categories help later

When you allocate a cost, tag what kind of cost it is: materials, subcontractors, plant and hire, or other. That lets you compare like with like against your quote. Overspending on materials tells a different story from overspending on hire.

Trade accounts and monthly statements

Most trade suppliers bill you per delivery and then send a monthly statement. The statement is a useful check, but it isn't the place to start allocating costs. By the time it arrives, the jobs may be finished and invoiced. Allocate each bill as it comes in, then use the statement to confirm nothing is missing and nothing has been billed twice.

Keep an eye on payment terms too. Many trade accounts expect payment by the 20th of the following month. Paying on time protects your account and your relationship with the supplier, which matters when you need a favour on a rush order.

How purchasing feeds job costing

Good purchasing and good job costing are the same habit seen from two sides. When orders, deliveries and bills are all linked to jobs:

  • You see materials costs on each job as they happen, not at month end.
  • Committed costs show you what's coming, so a job doesn't look better than it is.
  • Variances against your quote stand out early, while there's still time to do something about them.
  • Your quotes improve, because you can see what materials really cost on past jobs.

If you're finding that materials regularly blow out, the cause is often in the quote rather than on site. Our guide on how to write a job quote in New Zealand covers pricing materials properly.

How Tavo handles purchasing

In Tavo, purchase orders are raised against a job and a supplier, with the supplier's quote or reference, a needed by date and where to deliver. Lines can be typed in or added from your price book. You can email the PO to the supplier with a PDF attached, or mark it as ordered if you phoned it through or bought it over the counter.

When goods arrive, you record quantities per line, or press "It all came". Part deliveries are tracked, and late deliveries show up on the Home screen. Supplier bills come in from Xero (approved or paid bills) once it's connected, or you can enter a bill in Tavo and attach the PDF or a photo. Either way, you then charge the bill to jobs and PO lines with a category: materials, subcontractor, plant and hire, or other. Ordered but not yet received amounts count as committed costs on the job, so job costing shows the full picture.

To be clear about the limits: bills entered in Tavo aren't sent to Xero, Tavo doesn't track stock or inventory, there are no supplier price feeds, and supplier credits or returns can't be recorded in Tavo yet. If you run a workshop, such as an engineering and fabrication business, with lots of material moving through, it's worth trying on a few real orders. Tavo is free for 14 days, with no card needed.

This post is general information, not legal, tax or employment advice. Rules and rates change, so check the official source linked above or talk to an adviser, such as your accountant or a lawyer, before relying on it. Spotted something out of date? Let us know.